On shift: Diego Bettoni, Gabriele Garzoglio Continued data taking at the psi prime peak. The problem of too low instantaneous is still there, at present S. Werkema and B. Marsh are setting up a vertical scan. A scan of the jet target done this morning at the beginning of the shift showed that the H2 jet is OK. A few minor problems/remarks: - Online monitor shows a noisy channel for the FCAL. - FCAL OR rates from run 879 do not scale properly with the rates from the previous runs. - In the course of run 878 we observed a drop by a factor of 1.5 in the CCAL(1:3) rate and by a factor of almost 4 in the CCAL(18:20) rate. - DAQ hung up 4 times during the shift, in all cases the RESET button was enough to resume data taking. Summary of data taken during the shift: run 878 178.2 nb-1 run 879 169.6 nb-1 run 880 in progress Grand total at this energy (runs 877-879) : 531.4 nb-1 Diego and Gabriele