Shift Summary for 8:00-12:00 10/10/00 On Shift: AT,ZM Log Book #9 Page 27 Psi' peak Run: 7252 - stopped at 11:00 Comments: Beam dumped at 11:00. All the stop procedures and end of stack script run have been done. Have a good day, Amiran, Zaza KEG, GG, MN went downstairs to fix the problems we found during last stack. They found that the cable to power the luminosity monitor pre-amps not connected. They reconnected it and WR tested the luminosity monitor with the pulser and the source and said it was ok. StrawI HV cable was found broken. They replaced the cable with a spare one(stHV3). HV card channel HP-22 has a bad connector (cannot lock cable connector). We connect HP-22 HV cable to channel 25. The HV file has been updated. The new file is ~daqman/hv_new/bin/hv_10oct00.dat Saluti Stephen, Bombo, Margherita, Amiran, Zaza, Keith, Gabriele, Matteo, Willi.... P.S. many people's controlled access qualifications had lapsed.. many thanks to those whose qualifications are still current..